Our Projects — At a Glance

RhineBuild Group delivers complex infrastructure, public-sector, and industrial construction projects across Germany, Europe, and selected international markets. Our project portfolio reflects structured execution, engineering depth, and long-term responsibility across diverse project environments.

Project Portfolio Overview

Delivering infrastructure and construction projects across diverse sectors.

A panoramic view of a modern highway interchange under construction at dusk, highlighting engineering precision.
A panoramic view of a modern highway interchange under construction at dusk, highlighting engineering precision.
Transport & Mobility Infrastructure

Delivery of transport-related infrastructure including highways, roads, bridges, and mobility corridors. Projects focus on safety, durability, regulatory compliance, and long-term operational performance within public-sector frameworks.

building near trees during day
building near trees during day
Public & Urban Development

Construction of public buildings and urban infrastructure supporting civic services, institutional facilities, and urban growth. Projects are executed in close coordination with public authorities and regulatory stakeholders.

two large metal tanks sitting next to each other
two large metal tanks sitting next to each other
a very tall building in the middle of a city
a very tall building in the middle of a city
Industrial & Energy Projects

Execution of industrial facilities and energy-related infrastructure, including civil works and integrated construction solutions. Projects support industrial operations, energy generation, and long-term asset functionality.

Smart & Sustainable Infrastructure

Development of smart and sustainable infrastructure integrating modern construction methods, digital systems, and environmental considerations. Projects are designed to support efficiency, resilience, and future-ready operation.

Few of our Top Projects (Delivered )

RhineBuild Group has successfully delivered 500 Projects in last 35+ years, here are few of our top projects.

The EDGE East Side Tower — Berlin.
  • Type: High-rise residential tower (mixed-use with public ground-floor functions).

  • Height / Floors: ~142 m, 36 floors.

  • Gross floor area: 65,000 m² (office area); 80,000 m² gross floor area

  • Construction start: site prep 2019 / foundation works 2020–2021.

  • Completion / topping out: topping-out 2022; building completed and handed over in 2023 (interior works continued till mid 2024)

  • Development cost / budget: ~€400 million

Kö-Quartier Offices — Düsseldorf
  • Type: Modern office and commercial building complex.

  • Height / Floors: ~ 8 floors.

  • Gross floor area: 21,000 m² of gross floor area.

  • Construction start: site prep & foundation 2017

  • Completion / topping out: Building completed and handed over in 2020

  • Development cost / budget: ~€180 million

  • Type: High-rise residential apartment towers comprising mixed residential units, retail and communal spaces

  • Height / Floors: ~18- 21 floors per tower.

  • Gross floor area: 22,000–30,000 m²

  • Construction start: site prep & foundation works 2019

  • Completion / topping out: Building completed and handed over in 2023 (Interior works continued till mid 2024)

  • Development cost / budget: ~€210 million

HafenCity Residential Towers – Hamburg
  • Type: Mid-rise commercial office building (Multi-tenant office / business park)

  • Height / Floors: ~7-9 Floors.

  • Gross floor area: 18,000–25,000 m² including parking area

  • Construction start: site prep &foundation works 2016

  • Completion / topping out: Building completed and handed over in 2019

  • Development cost / budget: ~€110 million

The EDGE East Side Tower — Berlin.
  • Type: Premium automobile dealership & service centre use for Jaguar & Land Rover showroom, sales, service, and aftersales.

  • Height / Floors: ~142 m, 36 floors.

  • Gross floor area: 12,000 m²including parking

  • Construction start: site started in 2016

  • Completion / topping out: Building completed and handed over in 2019

  • Development cost / budget: ~€65 million

Land Rover Zentrum München
A7 Expansion – Elbtunnel Section (Hamburg)
  • Type: Highway infrastructure expansion project, Hamburg, Germany

  • Length/Area: Approx. 6–8 km of expanded highway corridor in the Elbtunnel urban section

  • Gross floor area: 12,000 m²including parking

  • Construction start: site started in 2015

  • Completion / topping out: Expansion phase completed and handed over in 2018

  • Development cost / budget: ~1.5 billion

  • Type: Offshore wind energy generation and grid infrastructure, North Sea, off the coast of northern Germany (near Hamburg energy corridor.

  • Capacity / Size: 900 MW – 1,200 MW installed capacity

  • Construction start: preparatory works in 2019-2020

  • Completion : Main phase completed in 2025

  • Development cost / budget: ~3.2 billion

Hamburg Offshore Wind Farm – Energy Infrastructure Project
Amazon Logistics Distribution Centre (FRA3 / FRA7)
  • Type: Large-scale logistics / distribution warehouse (Amazon fulfillment centre), Bad Hersfeld, Hesse, Germany.

  • Capacity / Floor Area: 110,000 m² (~17 football pitches)

  • Construction start: Site started in 2011

  • Completion : Handover completed in 2014

  • Development cost / budget: ~165 Million

Few of our Top Projects (Ongoing)

QuartierX City Mall
  • Project Name: QuartierX City Mall

  • Location: Berlin

  • Type: Multi-storey shopping mall (retail & commercial)

  • Gross Floor Area: ~38,000–45,000 m²

  • Construction Start: March 2025

  • Expected Completion: December 2027

  • Estimated Budget: ~€110–140 million

RheinVista Residences
  • Project Name: RheinVista Residences

  • Location: Riverfront district, Frankfurt

  • Type: High-rise luxury residential apartment (river-view)

  • Floors: ~18–22 storeys

  • Gross Floor Area: ~42,000–50,000 m²

  • Configuration: Premium apartments with river-facing balconies, podium amenities, and underground parking

  • Construction Start: June 2024

  • Expected Completion: Q4 2027

  • Estimated Budget: ~€160–190 million

Med Nexus Medical City
  • Project Name: MedNexus Medical City

  • Location: Stuttgart (multi-specialty healthcare campus)

  • Type: Multi-specialty hospital & medical college complex

  • Configuration: Tertiary care hospital, teaching blocks, research centre, diagnostics & support facilities

  • Floors: ~6–8 storeys

  • Gross Floor Area: ~85,000–100,000 m²

  • Capacity: ~750–1,000 hospital beds + academic facilities

  • Construction Start: January 2023

  • Expected Completion: Q2–Q3 2027

  • Estimated Budget: ~€280–320 million

  • Project Name: highway Link Interchange extension

  • Location: Hamburg Metropolitan Region, Germany

  • Type: Multi-level highway interchange & road expansion

  • Scope: Elevated flyovers, carriageway widening, bridge structures, traffic systems

  • Length / Area: ~7–9 km corridor

  • Construction Start: April 2025

  • Expected Completion: Q3 2027

  • Estimated Budget: ~€420–480 million

Med Nexus Medical City
Gerolsteiner Distribution Hub
  • Project Name: Gerolsteiner Distribution Hub

  • Location: Germany (industrial logistics zone)

  • Type: Large-scale FMCG warehouse & distribution centre

  • Structure: Steel structural warehouse with loading docks and logistics yards

  • Floors: Ground + mezzanine (1–2 levels)

  • Gross Floor Area: ~60,000–75,000 m²

  • Use: Storage, sorting, packaging & nationwide distribution

  • Construction Start: February 2025

  • Expected Completion: Q1 2027

  • Estimated Budget: ~€90–120 million